2025.07 Culvert Repairs

Construction Contract Information
Contractor:
C.L.H. & Sons, Inc.
Bid Amount: $3,002,508
Projected Completion Date: November 30, 2025

Crews-setting-out-concrete-barrier-in-Scarborough-in-May-2025.jpg

Project Scope: The work consists of culvert repairs at three locations. At the Dunstan River Culvert at MM 40.30 in the town of Scarborough, the work generally consists of constructing two access ways as needed and slip lining the existing 78” reinforced concrete pipe culvert with a 66” liner pipe. At the Unnamed Stream Culvert at MM 72.00 in the town of New Gloucester, the work generally consists of constructing two access ways as needed and slip lining the existing 60” reinforced concrete pipe culvert with a 54” liner pipe. At the culvert at MM 72.20, in the town of New Gloucester, the work generally consists of slip lining the existing 30” culvert with an ultraviolet light cured-in-place pipe (UV-CIPP).

May 2025 Update