Construction Contract Information
Contractor: Great Falls Construction
Bid Amount: $289,091.20
Projected Completion Date: October 31, 2026
Project Scope: Work consists of improvements to the Maine Turnpike Authority Headquarters Building and includes selective demolition and construction. Including a new nursing suite, and conference rooms. The work includes modifications to the mechanical, electrical, fire suppression, fire alarm and plumbing systems to support the upgrades.
September 2026 Update
July 2026 Update