2025.03 Pavement Rehabilitation, Safety Improvements & Pipe End Repairs MM 51.2 to 54.5

Construction Contract Information
Contractor:
Coastal Road Repair
Bid Amount: $6,565,928.00
Projected Completion Date: September 17, 2025

Turnpike-median-after-it-has-been-regraded-in-June-2025.jpg

Project Scope: The pavement rehabilitation work consists of milling and filling two travel lanes and the median and outside shoulders for both northbound and southbound approaches. Excess material in the median will be removed, and catch basins shall be cleaned to restore proper drainage. Guardrail height will be adjusted as necessary, with damaged sections of guardrail being replaced where it is needed. The splash pad at the outlet of the 48" culvert located on the eastside of the turnpike at station 2717+45 shall be supported by grout bags underneath the hanging end.