2024.12 Cleaning and Painting Steel Structures

Construction Contract Information
Contractor:
Saffro Construction, Inc.   
Bid Amount: $ 1,595,000.00
Projected Completion Date: November 21, 2025

Containment-equipment-on-a-bridge-before-it-is-painted-in-July-2025.jpg

Project Scope: The work consists of cleaning and painting the structural steel and metal work, and all non-galvanized bearing assemblies, with a three coat NEPCOAT paint system for Shaker Road Underpass Bridge, Weymouth Road Underpass Bridge, and Bennett Road Underpass Bridge