Construction Contract Information
Contractor: C.L.H & Sons, Inc
Bid Amount: $1,729,872.00
Projected Completion Date: November 30, 2026
Project Scope: This project includes culvert repairs at three locations along the Maine Turnpike: slip lining and access way construction at the Long Creek Culvert (MM 45.90) in South Portland, joint parging at the Unnamed Stream Culvert (MM 57.10) in Cumberland, and slip lining, access way construction, and headwall replacement at the Unnamed Stream Culvert (MM 91.30) in Litchfield.
June 2026 Update