2023.01 Pavement Rehabilitation & Drainage Improvements MM 88.6 TO MM 98.0


Construction Contract Information
Bid Amount: $8,659,704.25
Projected Completion Date: September 15, 2023
Contractor: Pike Industries, Inc.

mm98-(1).JPG


Project Scope: The pavement rehabilitation work consists of milling and paving full width (36 feet) from Mile 88.6 to Mile 92.8 and milling and paving two 12 foot wide lanes and the left inside shoulder for both northbound and southbound from Mile 92.8 to Mile 98.0. Excess material in the median will be removed to restore proper drainage, catch basins will be rebuilt and adjusted as necessary, drainage outlets will be replaced as necessary. Additional drainage work to be completed is located at mile marker 73.
 

October 2023 Update

August 2023 Update

July 2023 Update

June 2023 Update

May 2023 Update

April 2023 Update