Construction Contract Info
Contractor: Lane Construction Corp
Bid Amount: $2,913,072.50
Projected Completion Date: September 14, 2018
Project Scope: The pavement rehabilitation consists of milling and filling two 12-foot wide lanes and the four foot shoulder from mile marker 74.9 to 80.7 on the turnpike mainline and also includes paving of the Exit 75 ramps. The work also involves partial depth pavement repairs, earthwork, drainage, guardrail, pavement marking and maintenance of traffic.