Construction Contract Info
Contractor: Scott Construction Corporation
Bid Amount: $918,886.00
Projected Completion Date: November 16, 2018
Danville Corner Road Bridge (east fascia)
Project Scope: This project includes general repairs and modifications to various bridges between Mile 75 and Mile 92 of the Maine Turnpike. The locations are listed below.
The work includes pavement and membrane replacement, concrete deck, parapet, fascia, fascia overhang, pier, and abutment repairs, concrete wing wall and culvert wall repairs, bridge joint repairs, protective coatings, milling and paving and maintenance of traffic.