207-871-7771 877-682-9433

2018.06 Biddeford Interchange Pavement, Bridge Repairs & Route 111 Underpass Bridge Repairs


Construction Contract Info
Contractor:  Scott Construction Corporation
Bid Amount:  $2,678,148
Projected Completion Date:  October 12, 2018 
                                               

                    Crediford Brook Culvert                                         Route 111 Underpass Bridge
   
Crediford-brook.png       Route-111-underpass.png

Biddeford Interchange Bridge
Biddeford-Interchange-Underpass.png
 

Project Information Sheet

 
Project Scope:  The work consists of repairs to three structures at three locations for the Maine Turnpike Authority. It includes: substructure repairs at Crediford Brook Culvert, deck repairs, expansion joint replacement and modification, and substructure repairs at Route 111, pavement rehabilitation, deck repairs, expansion joint installation, and end post replacement at Biddeford Interchange and maintenance of traffic.

 

October 2018 Update

August 2018 Update

July 2018 Update

June 2018 Update

April 2018 Update