2018.01 Mainline Pavement Rehab Mile 98 to Mile 102

Construction Contract Info
Contractor:  Pike Industries, Inc.
Bid Amount: $2,448,806.70
Projected Completion Date: July 27, 2018

Project Scope:  The pavement rehabilitation work consists of milling and filling two 12-foot wide lanes and the four foot shoulder in areas between mile 98 and mile 102 on the turnpike mainline and the Exit 102 ramps--excluding areas around Cobbeessecontee Bridge and the West Gardiner ORT. The work also involves earthwork, drainage, guardrail, pavement markings and maintenance of traffic.
 

August 2018 Update

July 2018 Update

June 2018 Update


April 2018 Update