Falmouth Bridge Repairs: Blackstrap Road and Exit 52 Interchange Bridge

Construction Contract Info

Contractor:  CPM Constructors, Freeport
Bid Amount:  $3,523,168
Projected Completion Date: November 15, 2013

 



Blackstrap Road, Falmouth
Project Scope: The work consists of rehabilitation of the Blackstrap Road superstructure over the Maine Turnpike in the Town of Falmouth. The work includes concrete deck replacement, raising the bridge to increase the under clearance over the Turnpike, concrete substructure modifications, repairs and approach work.

Public Meeting Notice

Additional Project Information


                  December 20, 2012

Exit 52 Interchange Bridge, Falmouth
Project Scope: The work consists of rehabilitation of the Exit 52 Interchange bridge superstructure over the Maine Turnpike in the Town of Falmouth. The work includes replacement of the bridge railings, raising the bridge to increase the under clearance over the Turnpike, concrete substructure modifications, repairs and approach work.

Additional Project Information

Public Meeting Notice


March 2013 Update

April 2013 Update

May 2013 Update

June 2013 Update

July 2013 Update

September 2013 Update

October 2013 Update

November 2013 Update



 

  • Follow us
Maine Turnpike Authority © 2012
Maine Web Design by Lighthouse Web Solutions