2018.21 Interstate 195 Culvert Linings

Construction Contract Info
Contractor: Ted Berry Company
Bid Amount: $26,3704.80
Projected Completion Date: October 31, 2018
 
culvert-lining.jpg


 
Project Scope:  The work consists of lining two existing culverts under Interstate 195 in the city of Saco,
Maine. The 42” diameter Goosefare Brook culvert is located approximately 0.25 miles west of the
I-195 toll booths where the southbound entry and exit lanes cross Goosefare Brook. The 36”
diameter unnamed tributary to Goosefare brook culvert is located approximately 200 feet west of the
I-195 toll booths. The work includes lining of the existing culverts with a UV light cured-in-place
pipe (CIPP), placement of riprap armoring, filling an existing erosion hole, maintenance of traffic.
 

October 2018 Update

August 2018 Update