2017.03 Maxwell Road Bridge

Construction Contract Info
Contractor:  Reed & Reed, Inc.
Bid Amount:  $1,796,866.00
Projected Completion Date: November 17, 2017

Maxwell-Road-bridge.jpg

Project Scope:  The Project consists of highway and bridge work required to replace the existing one lane Maxwell Road bridge over the Maine Turnpike in the Town of Sabattus, Maine. The work includes
clearing, grading, drainage, base, pavement, guardrail, structural concrete, concrete deck, fabrication
and erection of steel beams, steel bridge rails, and maintenance of traffic.

Project Information Sheet & Detour Route  

Bridge Closed: Monday, April 3, 2017

October 2017 Update

August/September 2017 Update

July 2017 Update


June 2017 Update

May 2017 Update

April 2017 Update

March 2017 Update 

February 2017 Update