2015.05 Wells Exit 19 Interchange Improvements


Construction Contract Info
Contractor: Pratt & Sons, Inc.
Bid Amount:  $353,083
Projected Completion Date:  October 30, 2015



 
Project Scope:  The project includes construction of an additional lane between the toll plaza and Route 109 exiting the turnpike.  This will provide for a left turn lane, a through left turn lane and a right turn lane at the intersection for the turnpike exit.  Additional improvements include relocation of the traffic signal cabinet to be further away from the corner, replacment of the traffic signal controller, installation of an emergency pre-emption system at the intersection and installation of a new video vehicle detection system for the intersection. 

October 2015 Update

August 2015 Update

July 2015 Update